Beach Renourishment Underway from November 18 – Mid-January

(Monday, October 21, 2019) – The Estates at Acqualina project will be completing a beach sand re-nourishment from approximately Terracina Avenue (northern City limit) to 185 Street. During this time, the beach will remain open but access may be partially modified. A temporary construction fence will be set up on the beach in the affected areas for the safety of beachgoers.

The project will begin on Monday, November 18, 2019, with an expected duration of 8-9 weeks, with completion around mid-January. Project hours are 7:30 am – 5:30 pm on weekdays. Although work is permitted on Saturdays per City Code, it will only take place if needed to catch up due to unforeseen delays. No work will take place on Sundays or on holidays.

Questions or concerns, please contact:

Nicholas Machin, Assistant Project Manager
PH: 786.810.5921
EM: nicholas.m@gonzalezandsons.net

or

Javier Slaton, Project Manager
PH: 305.890.6532
EM: javier.s@gonzalezandsons.net

Beach Renourishment MOT Map