Collins Avenue Undergrounding Remedial Asphalt Repairs

Thursday, August 3, 2017 —

By City Manager Chris Russo

As of August 1, 2017, 1,854 Linear Feet (LF) of repairs have been accomplished from 180th Street southbound to 172nd Street. 600 LF of the main trench southbound from 172nd Street to Haulover Park was completed August 2, 2017.

The northbound 1000 LF of main trench from Haulover Park to Golden Beach remains to be completed.

At night on August 3, 2017, the work area will shift to the northbound lanes from 183rd Street to 191st Street, which are the worst areas remaining.

The work will then return to filling in the miscellaneous southbound areas and then move to the remaining northbound areas once southbound is completed.

Primary focus will remain on the main trench as it has the most challenging driving conditions; however, left side laterals are being accomplished along with main trench work. Once all main trenches are rectified, right side laterals will be completed. It is done in this manner to keep traffic flowing.

Work has been authorized to be done both Friday and Saturday nights this week.

The entire project, weather permitting and asphalt plants open should be completed by approximately August 13, 2017.

I am available at any time if you have further questions or need additional information.

Chris Russo