How much time do I have to get the work done once a permit is issued?

A permit will expire and become null and void if work is not started and an approved inspection is not obtained within 180 days from the issuance date of the permit. After such work has commenced, the permit will expire when work is suspended or abandoned for a period of 6 months unless an approved inspection is obtained.