Florida Department of Transportation Logo

FDOT Bridge Rehabilitation Project on SR 856/William Lehman Causeway

Construction Activities

Drainage operations, concrete and bridge repairs

  • Construction Activity
    • Performing bridge repairs under the east side of the causeway
    • Performing drainage operations along the causeway
    • Performing concrete restoration

FDOT Bridge Rehabilitation Project on SR 856/William Lehman Causeway has been completed.

Work Performed

  • Cleaning and painting the bridge and repairing the steel structures
  • Repairing bridge deck and underside concrete
  • Repairing bridge drainage
  • Replacing traffic delineators on the bridge

Project Schedule

Early 2021 – Fall 2021

Lane Closure and Detour Information

To do this work safely, it will be necessary to close travel lanes and sidewalks during nonpeak hours. Lanes may be closed:

  • 9 am to 3:30 pm, weekdays and weekends
  • 9 pm to 5:30 am, Sundays through Thursdays
  • 11 pm to 7 am, Fridays and Saturdays

Ramp closures will also be necessary to perform work. Ramp closures will occur during nonpeak hours and a detour will be posted. Lane closures and project information will be posted weekly on the department’s website.

Please allow extra time to reach your destination and obey all posted signs and speed limits.

FDOT will post the latest updates, including scheduled lane closures, on their webpage.

For current lane closures in Sunny Isles Beach, visit sibfl.net/news.

For more information, contact:
Melissa J. Rodriguez
FDOT Community Outreach Specialist
305.570.8076
melissa@hmlpublicoutreach.com